Interstate 75 Construction
- From now through November, I-75 will be reduced to ONE LANE between Perrysburg and Findlay (Co. Rd. 99) between 7 pm and 6 am
- From now through December, I-75 will be ONE LANE from ROACHTON RD. AND ROUTE 20 (Northern part of the county)
- Through 2016, I75 will be TWO LANES from Route 20 to I-475
- Through 2016, 11’ lane restrictions will be from Route 20 to Findlay (Co. Rd. 99)
- June 9 at 8 pm to June 10 and 6 am, redirection of traffic will begin. ONE LANE will be open will be open during these hours
- June 10, Midnight to 5:00 am – the ramp from southbound I-75 to the BG Exit will be CLOSED. It will reopen at 5:00 am.
- Through December 2015 the ramp from Southbound I-75 to Westbound I-475 will be reduced to ONE LANE
- The ramp from Eastbound I-475 to Northbound I75 is PERMANENTLY reduced to ONE LANE
LOCAL CHANGES:
June 15 through October, Jerry City Road at I-75 will be closed for bridge work